Mumbai Real Estate News: MahaRERA Orders Dahisar Project Promoters To Pay Interest For Delayed Flat Possession

Mumbai Real Estate News: MahaRERA Orders Dahisar Project Promoters To Pay Interest For Delayed Flat Possession

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has directed the promoters of the Dahisar-based project “VKLAL Vishnu Phase-1” to pay interest to three complainants for the delay in handing over possession of their flats.

Pranali LotlikarUpdated: Wednesday, October 01, 2025, 09:18 PM IST
article-image
Homebuyers celebrate MahaRERA ruling as Dahisar project promoters ordered to pay interest for delayed possession | Representational Image

Mumbai: The Maharashtra Real Estate Regulatory Authority (MahaRERA) has directed the promoters of the Dahisar-based project “VKLAL Vishnu Phase-1” to pay interest to three complainants for the delay in handing over possession of their flats.

Complaint by Homebuyers

The complainants, represented by advocate Anil D’Souza, had booked their respective flats in the project developed by Veekaylal Investment Co. Pvt. Ltd., Khushi Builder & Developer, and Tyabji Estates Pvt. Ltd. They alleged that despite paying over half the total consideration for their flats, the developers failed to deliver possession as promised.

Delay in Possession

According to the registered agreements for sale, the developers were obligated to hand over the flats by December 2021 and June 2022. However, the possession was delayed without any concrete assurance from the promoters.

Aggrieved by the breach of contract, the buyers approached MahaRERA seeking possession with occupancy certificates, along with interest and compensation for the delay.

MahaRERA’s Directive

In its order, MahaRERA directed the respondent promoters to pay interest on the amount paid by the complainants towards the cost of the flats—excluding stamp duty, registration charges, and taxes—at the State Bank of India’s Marginal Cost Lending Rate (MCLR) plus 2%, as prescribed under Section 18 of the RERA Act.

Interest Calculation and Payment Terms

The interest will be calculated from January 1, 2023, for one complainant and from July 1, 2022, for the other two, until the date of the offer of possession with a valid occupancy certificate.

However, considering the mitigating circumstances such as delays due to the Covid-19 pandemic and to avoid jeopardizing the completion of the project, MahaRERA allowed the developers to pay the interest only after obtaining the full occupancy certificate.

The authority further clarified that if the interest payable by the developers exceeds the outstanding dues of the complainants as of the date of the order, the developers will not be entitled to raise any further demand for the balance amount. Instead, the interest amount will be adjusted against the dues to avoid future disputes.

Developers’ Arguments

The developers argued that they are reputable builders known for timely delivery of projects and claimed that the delays were beyond their control, citing the pandemic and the pending occupancy certificate application submitted by their architect on December 12, 2024. They also sought dismissal of the complaint, contending that it was non-maintainable under procedural rules.

Also Watch:

MahaRERA Upholds Buyers’ Rights

MahaRERA, however, upheld the homebuyers’ claims and reinforced that delays in possession, regardless of external factors, entitle buyers to compensation under the provisions of RERA.

To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/

RECENT STORIES

Planning Travel From Upcoming Navi Mumbai International Airport? Check Out Premium Hotels Within...

Planning Travel From Upcoming Navi Mumbai International Airport? Check Out Premium Hotels Within...

‘Dirty Mentality’: Mumbai Sessions Court Sentences 40-Year-Old Man To Life Imprisonment For...

‘Dirty Mentality’: Mumbai Sessions Court Sentences 40-Year-Old Man To Life Imprisonment For...

Farmers’ Identities Exploited In ₹152-Crore Bank Scam: ED Uncovers Over ₹100 Crore Assets...

Farmers’ Identities Exploited In ₹152-Crore Bank Scam: ED Uncovers Over ₹100 Crore Assets...

Mumbai’s 7 Lakes At 98.70% Capacity, BMC Confident Of Adequate Water Stock Until June 2026

Mumbai’s 7 Lakes At 98.70% Capacity, BMC Confident Of Adequate Water Stock Until June 2026

Mumbai Crime: 27-Yr-Old Man With Criminal Record Arrested For Attempted Murder Over Road Rage In...

Mumbai Crime: 27-Yr-Old Man With Criminal Record Arrested For Attempted Murder Over Road Rage In...