Mumbai News: Metro 2B To Ply Above Monorail, Thanks To U-Girder
Notably, the infrastructure was launched while the Monorail was in operation; there was no room for error, says official.

Representational Image | Vijay Gohil/FPJ
A crucial milestone was achieved during the wee hours of Saturday when a girder of Metro 2B line was launched over an operational Monorail line at Vashi Naka, Chembur. “The launching of U-girder (the structure on which the Metro will ply) was crucial as it had to be ensured that no damage or danger is posed to the operational Monorail line. There was no room for error,” said an official.
Metro 2B will connect Andheri West with Mandale in Mankhurd via Bandra, while the Monorail operates between Chembur-Wadala-Jacob Circle. Both the public transportation systems are under the Mumbai Metropolitan Region Development Authority’s (MMRDA’s) fold. “As the U-girder had to be lifted and placed 5.6 metres above the Monorail’s guideway beam, a crane of 750 metric tonnes capacity was deployed (for the heavy lifting). For other U-girder launches, we deploy a crane having a capacity of 250-300 metric tonnes,” explained the MMRDA official.
The construction of Metro 2B began back in April 2018 and the authorities plan to make a section, stretching from Mandale to Diamond Garden, by mid-2024. This will be about a 5 km route having the stations of Mandale, Mankhurd, BSNL, Shivaji Chowk and Diamond Garden. At Shivaji Chowk, the line will cross the junction below the Eastern Freeway near the RK Studios.
The Monorail is on Ramkrishna Chemburkar Road, while Metro 2B is being constructed on V N Purav Road. Both the modes of transport mode intersect at Vashi Naka.
Key Details
Location: Vashi Naka
Workforce involved in girder launch: 35
No. of traffic warden present: 15
Gap between Monorail beam and Metro U-Girder: 5.6 metres
Girder's height from ground: 18 metres
Time taken for launch: 6 hours
RECENT STORIES
-
WCL 2025: Yusuf Pathan Hugs & Kisses Kids In Celebration After Helping India Champions Beat West... -
India’s Green Steel Demand Set For Exponential Growth, To Escalate 179 Million Tons By FY50 -
Average Monthly Net GST Collection Rises By 10.7% To ₹1,80,774 Crore In The First Quarter -
UP Health Dept Observes World ORS Day With 'Stop Diarrhoea' Workshop, Aims For Zero Child Deaths -
Skanda Sashti 2025: Date, Puja Vidhi And Significance