Mumbai: MahaRERA Grants Extensions To Housing Projects By Rustomjee Crown, Rustomjee Summit & Raunak Unnati Woods Phase VIII
The extensions have been made under Section 7 (3) of RERA.

Representational photo |
Three Housing Projects in Mumbai - Rustomjee Groups’s Rustomjee Crown Phase 1 in Prabhadevi, Rustomjee Summit in Borivali East and Raunak Groups Unnati Woods Phase VIII in Thane have been granted extensions in their completion dates by the Maharashtra Real Estate Regulatory Authority (MahaRERA). The extensions have been made under Section 7 (3) of RERA.
In his regulatory order, MahaRERA chairman Ajoy Mehta observed: “…it is clear that the whole aim of the Act has been to promote the real estate sector efficiently and transparently and protect the interest of the consumers. Thus, by not extending the registration of the project, the same will come to a halt.
ALSO READ
The promoter shall not be able to take actions for efficient completion as may be required in view of the lack of registration. Such an action will only be detrimental to the interest of the consumers. This balance of convenience lies in allowing the extension with such condition to ensure completion.”
Real Gem Builtech Pvt Ltd, the promoter-developer of the Rustomjee Crown project, applied for an extension of its completion date from December 31, 2023, to December 31, 2024. During the hearing, the promoter cited delays due to the Covid-19 pandemic, geopolitical tensions, MCGM notification changes, and shortage of building materials. The project is almost 86 per cent complete and they intend to handover the possession at the earliest.
Though the original completion date was December 31, 2021, MahaRERA had previously granted three extensions till December 31, 2023, considering the pandemic. RERA provisions state that the promoter needs to obtain the consent of 2/3rd of homebuyers who have booked apartments in the project if any change in plans or completion date is required. However, Section 7(3) of RERA allows authorities to keep a project’s registration intact by setting conditions that protect home buyers’ interests. Promoters must follow these conditions.
ALSO READ
Similarly, an extension was granted to the Rustomjee Summit project in Borivali East, with the completion date extended from December 31, 2023, to December 30, 2024. Keystone Realtors, the promoter, highlighted obtaining the Occupancy Certificate(OC) for floors 1 to 38 in August 2023 and they were in the process of obtaining OC for the last two floors.
MahaRERA also extended the completion date for the Unnati Woods project in Kavesar Thane, a single residential building. The promoter, Rajan Bandelkar of Raunak Group, explained changes in government policy allowing additional construction floors. The extension directs the developer to obtain the Occupancy Certificate for up to 24 floors by June 30, 2025, and complete construction up to the 45th floor by December 31, 2027.
RECENT STORIES
-
Indore: Digital Working In All Government Offices From May 5 -
MP Transco Boosts City’s Power Supply With New 50 MVA Transformer -
3 Pak Citizens On Short-Term Visas Deported From Indore -
FPJ Interview: Kashmir After Pahalgam Attack – Responsibility, Reality And Road Ahead; VIDEO -
Rahul Gandhi To Begin 2-Day Visit To Rae Bareli & Amethi On April 29