Mumbai: BMC Prepares To Connect Coastal Road With Worli-Bandra Sea Link
Spanning 850 meters, the linkage between the coastal road's Worli terminus and the sea link primarily consists of 270 meters of steel and the remainder concrete.

Mumbai: The Brihanmumbai Municipal Corporation (BMC) has taken a significant step forward in its coastal road project by loading a 2000 metric tonne, 136-meter span bowstring arch onto a barge at Mazgaon Dock Jetty (Nhava) on Sunday.
This prefabricated and pre assembled structure is set to connect the coastal road with the Bandra Worli Sea Link, aiming to alleviate southbound traffic congestion.
ALSO READ

The connection between the southbound arm of the Coastal Road and the Bandra-Worli Sea Link is scheduled to be completed by April 17, filling a crucial gap in Mumbai's coastal infrastructure.
ALSO READ

Spanning 850 meters, the linkage between the coastal road's Worli terminus and the sea link primarily consists of 270 meters of steel and the remainder concrete.
RECENT STORIES
-
War 2 Advance Booking Report: Hrithik Roshan, Jr NTR And Kiara Advani Starrer To Take A Low Start At... -
Kerala Lottery Result: August 13, 2025 - Dhanalekshmi DL-13 Live! Wednesday's Draw Reveals Winners... -
UP Legislators Launch ‘Friends Of MSMEs’ Platform To Boost State’s Economic Growth -
26/11 Mumbai Terror Accused Tahawwur Rana's Judicial Custody Extended Till September 8 By Special... -
Malhar 2025: Mumbai's St. Xavier’s College Announces Star-Studded Conclave Lineup; Check Who's On...