Indore-Khandwa Gauge Conversion Clears Key Hurdle; Forest Nod Received After 2 Years
According to official sources in both Railway and Forest departments, the approval was long awaited

Indore-Khandwa Gauge Conversion Clears Key Hurdle; Forest Nod Received After 2 Years |
Indore (Madhya Pradesh): In a major breakthrough for the long-pending Indore-Khandwa Gauge Conversion (GC) project, the Forest Department has finally given its approval for a critical stretch between Patalpani and Mukhtyara, clearing the way for construction work to commence after a delay of more than two years.
The go-ahead came on Monday from the Project Screening Committee-1 (PSC-1) of the Forest Department, a move that unblocks work on a 65 km stretch running through challenging hilly terrain. The area, which falls largely under forest jurisdiction in Mhow tehsil, had been holding up progress due to clearance delays.
According to official sources in both Railway and Forest departments, the approval was long awaited. “The proposal will now be forwarded to the Chief Minister’s Office, and subsequently to the Ministry of Railways,” they said, requesting anonymity.
ALSO READ
The construction department of Western Railway had submitted the forest land acquisition proposal back in January 2023. Since then, the project was stuck pending environmental and land-use clearance. Officials said the Forest Department is now conducting GPS-based mapping to count and identify trees that may be affected by the railway alignment.
The 160 km long Indore-Khandwa GC project is one of the most ambitious and topographically complex railway works in the state. While gauge conversion has been completed across most sections, the remaining 65 km stretch between Mukhtyara (near Omkareshwar) and Patalpani remained unfinished due to its rugged geography—characterised by high hills, deep trenches and dense forest cover.
Initially, Western Railway had planned 21 tunnels along this segment to tackle the terrain. However, the plan has now been revised to 19 tunnels, aiming to simplify construction and reduce impact on environment.
With forest clearance now granted, railway authorities are preparing to kick-start physical work on this last and most challenging leg of the project. Once complete, the gauge conversion will significantly improve rail connectivity between Indore and southern parts of Madhya Pradesh, including Khandwa and Omkareshwar.]
RECENT STORIES
-
Electric Vehicle Sales In India Rise 28.60% To 1,80,238 Units In June, Driven By Massive Jump In... -
Pune: Cop Hangs Himself In Swargate; 4th Case Of Suicide In Last 6 Months -
'Mumbai's Sanjay Gandhi National Park Home To 54 Leopards': Maharashtra Forests Minister Ganesh Naik -
UP Board 10th, 12th Scrutiny Result 2025 Declared At upmsp.edu.in; Get Direct Link Here -
Hindustan Power Commences Work On 435 Megawatt Peak Solar Power Project At Lalitpur In Uttar Pradesh...